Foundation calculator: concrete, formwork, excavation and backfill

Up to three steps, rectangular or round, founding depth and pit: the tool gives concrete, formwork area, excavation, backfill and the soil left over – for one foundation or for all four corner foundations of a tower.

Register for free Read more in the manual

1 location free, no payment details. Runs in the browser – nothing to install. Try it without registering

Foundation in the tool: concrete, formwork, excavation and surplus, section through foundation and pit, checklist
Example from the sample project

What the tool calculates

Block, stepped, round

Up to three steps on top of each other, each rectangular or round – plus bored piles with diameter and length if required.

Pit included

Bottom from the lowest step plus working space, vertical or sloped; the checklist compares working space and slope with DIN 4124.

Quantities for several

Enter the number of identical foundations – for example four for the legs of a tower.

In the foundation workflow

At the location the foundation takes over the dimensions of the pit; tower foot and tower build on it, and the 3D view shows what is already there.

How to proceed

  1. Create the foundation at the location. On the location page – after the excavation pit it starts with its dimensions.
  2. Enter the steps. From bottom to top; every change is calculated and drawn immediately.
  3. Read checklist and comparison. Founding depth, top level, working space, slope – and whether foundation and pit match.
  4. Save. The quantities appear in the project's quantity overview, across all locations.

Inputs, results and calculation method

What you enter

  • Number of identical foundations
  • Steps: shape, length, width or diameter, height
  • Founding depth, blinding layer
  • Working space, slope angle or shoring, soil to DIN 4124
  • Reuse, bulking factor, concrete density, reinforcement content, piles

What you get

  • Concrete in m³ and t, reinforcement in kg
  • Formwork area, blinding layer
  • Excavation in situ and loose, backfill, surplus
  • Section through foundation and pit, 3D view, checklist
  • Pile concrete and spoil if piles are entered

How it is calculated

  • Per step: rectangular V = L · B · h, formwork = 2 · (L + B) · h; round V = π · D² ÷ 4 · h, formwork = π · D · h.
  • Pit with bottom a × b and depth t: vertical V = a · b · t; sloped V = t ÷ 6 · (a·b + (a + a′)·(b + b′) + a′·b′) with a′ = a + 2 · t ÷ tan β.
  • Backfill = excavation − concrete below ground − blinding layer; surplus = excavation − backfill.

The volumes are plain solid geometry. The checklist checks working space, vertical wall height and slope angle against the values of DIN 4124 – the same as in the excavation pit simulation. Go to the chapter in the manual

An example, recalculated

Slab 3.00 × 3.00 × 0.80 m with plinth 1.00 × 1.00 × 1.60 m, founded 2.00 m deep, 60° slope. The figures are calculated by the same engine as in the application – when this page is opened.

Step 1 (slab)
3.00 × 3.00 × 0.80 m
Step 2 (plinth)
1.00 × 1.00 × 1.60 m
Founding depth
2.00 m
Blinding layer
0.05 m
Working space / slope
0.50 m / 60°
QuantityResultCalculation
Concrete8.80 m³ · 21.1 t3.00 · 3.00 · 0.80 + 1.00 · 1.00 · 1.60
Formwork16.0 m²side faces of both steps
Blinding layer0.51 m³slab footprint with projection · thickness
Excavation pit2.05 m deep, 6.37 m wide at the topfounding depth + blinding layer; bottom + 2 · depth ÷ tan 60°
Excavation, in situ56.04 m³frustum: t ÷ 6 · (a·b + (a + a′)·(b + b′) + a′·b′)
Backfill47.13 m³excavation − concrete below ground − blinding layer
Surplus soil8.9 m³excavation − backfill

With an excavation pit at the same location the foundation takes over its dimensions – and the comparison shows every deviation.

Estimate a foundation

No login, nothing saved: enter values, and the result is calculated by the same engine as in the application.

Concrete
8.80 m³ 21.1 t
Formwork
16.0 m² side faces of all steps
Excavation
56.0 m³ in situ · 70.0 m³ loose
Backfill
47.1 m³
Pit
2.05 m deep 6.37 × 6.37 m at the top
  • Build-up met
    2 steps, 2.40 m high in total – each stands fully on the one below.
  • Founding depth met
    2.00 m below ground – at least 0.80 m is customary for frost-free founding in Germany; more applies regionally.
  • Top edge met
    The foundation projects 0.40 m above ground.
  • Working space met
    0.50 m per side – DIN 4124 requires at least 0.50 m if work is carried out in the working space.

Rectangular slab with plinth, pit with 0.50 m working space and 60° slope. In a project: round steps, piles, shoring, 3D view and the workflow pit → foundation → tower foot.

Save in a project – with PDF, 3D and team

Limits

What the tool does not do – so that it is clear what the result is good for. Results are planning aids, not construction documents.

  • No design: neither stability (overturning, sliding, uplift, bearing failure) nor reinforcement, concrete grade or settlement. Dimensions and founding depth come from the structural design and the ground investigation.
  • Steps are cuboids or cylinders with vertical sides, centred on top of each other; slopes and haunches are not modelled.
  • Not included: anchor cages, embedded parts, recesses, earthing, drainage, dewatering.
  • The frost-free founding depth of 0.80 m is a minimum common in Germany; regionally more applies.

Frequently asked questions

How much concrete does a foundation need?

Length times width times height per step. A slab 3.00 × 3.00 × 0.80 m with a plinth 1.00 × 1.00 × 1.60 m needs 8.80 m³ – at 2.4 t/m³ that is 21.1 t.

Does the tool also calculate the pit?

Yes, a rectangular pit per foundation from working space and slope. Shared pits, terrain and stockpiles are calculated by the excavation pit simulation at the same location.

Does this replace the structural design?

No. The tool determines quantities from dimensions you specify. It does not design anything.

Try it on your next construction project.

One location free, all tools. No credit card, no subscription.