Skip to content

Calculating excavation and stockpiles

More comes out of an excavation pit than fits back in: soil bulks when it is loosened, and a stockpile needs slopes. If you calculate excavation and storage area early, you know whether the soil stays on the plot or is hauled away.

As of: · baustellen.tools

What the excavation consists of

The excavation is the volume between the terrain and the excavated surface: the base (structure plus working space) and above it the slope. The excavation pit simulation places both as an elevation model on a grid and counts – so the quantity is also right for sloping terrain, several depths and freely drawn shapes.

Separating topsoil and subsoil

Topsoil is stripped and stored separately. It is calculated as a layer of constant thickness below the terrain, limited to the area that is excavated at all; at the edge, where the pit is shallower than the layer, only the actual depth counts. The rest is subsoil.

In place, loose, placed

“In place” is the undisturbed soil, “loose” the loosened soil: loose = in place · bulking. As a default the simulation calculates with 1.40 for topsoil and 1.30 for subsoil – the factor has to be adapted to the soil on site. For transport and stockpile, the loose volume counts.

How big the stockpile gets

A stockpile is a solid with a rectangular base and slopes on all sides. With base b × l, height h and slope 1 : n it holds V = h · (b · l − n · h · (b + l) + 4 ÷ 3 · n² · h²). Without a given base width, the square stockpile is the one with the smallest footprint; with a base width, the formula can be solved for the length.

Example – recalculated by the program

Separating and storing the excavation: the 10 × 8 m pit from above, plus a stockpile for 1200 m³

Excavation pit: 10 × 8 m, 3.00 m deep, slope 45°, working space 1.00 mTopsoil: 30 cmBulking: 1.40 topsoil · 1.30 subsoil

QuantityCalculationResult
Total excavation, in situfrom the terrain grid586.27 m³
of which topsoil30 cm over the excavated area, less at the edge81.3 m³
of which subsoil586.27 − 81.28504.99 m³
Topsoil stockpilebase 8 m, height 2 m – length from the bulked volume8 × 11.26 m
Subsoil stockpilebase 10 m, height 3 m10 × 33.83 m
1200 m³ loose, 2 m high, slope 1 : 1laid out as a square (smallest footprint)26.47 × 26.47 m, utilisation 86 %
the same stockpile with a base width of 20 mformula solved for the length20 × 35.26 m

The stockpile is always larger than the volume suggests: the slopes cost space – here 14 % of the circumscribed cuboid.

The figures are calculated by the same calculation core as in the application – every time this page is called up.

Limits

  • The quantities are as accurate as the inputs and the grid spacing; for billing, the site measurement applies.
  • The length of the stockpiles applies to a stockpile sloped at 45° all round – if the soil lies flatter, the stockpile needs more area.
  • Whether the excavated soil is suitable for reuse is decided by the soil investigation.
  • The terrain is a plane with two gradients; it does not represent hollows and edges.

This article is a working aid. It is not legal advice and does not replace specialist planning, a ground investigation report, structural analysis or a check by a competent person. The current editions of the standards and rules named here and the requirements of the client, the network operator and the authorities are authoritative. This is a translation; the rules cited are German and European ones, and the German version of this article prevails.

Sources and standards

  • DIN 4124 (excavations and trenches) for slope and working space.
  • Manual, chapters Excavation pit simulation (calculation method with a check calculation by hand) and Site layout (stockpile).

Calculate excavation and stockpiles Calculation method in the manual