Foundation quantities for towers: concrete, formwork, excavation
Before the first concrete is ordered, work preparation needs five figures: concrete, formwork, excavation, backfill and the soil that is left over. They all follow from the dimensions of the foundation and the pit.
As of: · baustellen.tools
Concrete and formwork per step
A stepped foundation is calculated step by step, from bottom to top. Rectangular: V = L · B · h, formwork area = 2 · (L + B) · h. Round: V = π · D² ÷ 4 · h, formwork area = π · D · h. Concrete in tonnes is the volume times density.
The pit for it
The base is the lowest step plus twice the working space; the depth is the foundation depth plus the blinding layer. Vertical: V = a · b · t. Sloped at angle β, the pit becomes wider at the top by 2 · t ÷ tan β in each direction, and the volume is that of a truncated pyramid: V = t ÷ 6 · (a·b + (a + a′)·(b + b′) + a′·b′).
Backfill and surplus
Backfill = excavation − concrete below ground level − blinding layer. The surplus is excavation minus backfill – that is, exactly what concrete and blinding layer take up in the ground. Without reuse, the whole excavation is surplus. For transport, the loose volume counts: loose = in place · bulking.
Four foundations per tower
A lattice tower on four legs has four single foundations. The quantities of one foundation are then multiplied by the number 4 – if you forget it, you order a quarter. If the pits lie close together, a comparison with a common excavation pit is worthwhile: the excavation pit simulation has the shape with four beams for this.
Example – recalculated by the program
Slab 3.00 × 3.00 × 0.80 m with plinth 1.00 × 1.00 × 1.60 m, founded 2.00 m deep, 60° slope
Step 1 (slab): 3.00 × 3.00 × 0.80 mStep 2 (plinth): 1.00 × 1.00 × 1.60 mFounding depth: 2.00 mBlinding layer: 0.05 mWorking space / slope: 0.50 m / 60°
| Quantity | Calculation | Result |
|---|---|---|
| Concrete | 3.00 · 3.00 · 0.80 + 1.00 · 1.00 · 1.60 | 8.80 m³ · 21.1 t |
| Formwork | side faces of both steps | 16.0 m² |
| Blinding layer | slab footprint with projection · thickness | 0.51 m³ |
| Excavation pit | founding depth + blinding layer; bottom + 2 · depth ÷ tan 60° | 2.05 m deep, 6.37 m wide at the top |
| Excavation, in situ | frustum: t ÷ 6 · (a·b + (a + a′)·(b + b′) + a′·b′) | 56.04 m³ |
| Backfill | excavation − concrete below ground − blinding layer | 47.13 m³ |
| Surplus soil | excavation − backfill | 8.9 m³ |
With an excavation pit at the same location the foundation takes over its dimensions – and the comparison shows every deviation.
The figures are calculated by the same calculation core as in the application – every time this page is called up.
Limits
- The tool determines quantities and designs nothing: dimensions, concrete grade, reinforcement and foundation depth are specified by the structural design and the ground investigation report.
- The calculation does not replace a stability analysis of the foundation or the tower.
- The excavation is calculated by formula for level terrain; the excavation pit simulation calculates with a terrain model, connectors and berms and therefore arrives at different values.
- Enter excavation pits deeper than 1.25 m only when sloped or shored.
This article is a working aid. It is not legal advice and does not replace specialist planning, a ground investigation report, structural analysis or a check by a competent person. The current editions of the standards and rules named here and the requirements of the client, the network operator and the authorities are authoritative. This is a translation; the rules cited are German and European ones, and the German version of this article prevails.
Sources and standards
- DIN 4124 (excavations and trenches) for slope angle and working space of the pit.
- Manual, chapter Foundation: calculation method and example.
Calculate a foundation Calculation method in the manual
More articles
- Site layout plan: what belongs in it and how to build it up
- Slope angle and working space according to DIN 4124
- Calculating excavation and stockpiles
- Pipe trench: minimum width according to DIN EN 1610
- Escape and rescue plan: what belongs on the sheet
- Calculating cable pulling tension and sidewall pressure
- Choosing a cable drum: how much cable fits on which drum?
- Sag and conductor tension in a span
- Swept path: will the delivery get round the corner?