Foundation quantities for towers: concrete, formwork, excavation

Before the first concrete is ordered, work preparation needs five figures: concrete, formwork, excavation, backfill and the soil that is left over. They all follow from the dimensions of the foundation and the pit.

As of: · baustellen.tools

Concrete and formwork per step

A stepped foundation is calculated step by step, from bottom to top. Rectangular: V = L · B · h, formwork area = 2 · (L + B) · h. Round: V = π · D² ÷ 4 · h, formwork area = π · D · h. Concrete in tonnes is the volume times density.

The pit for it

The base is the lowest step plus twice the working space; the depth is the foundation depth plus the blinding layer. Vertical: V = a · b · t. Sloped at angle β, the pit becomes wider at the top by 2 · t ÷ tan β in each direction, and the volume is that of a truncated pyramid: V = t ÷ 6 · (a·b + (a + a′)·(b + b′) + a′·b′).

Backfill and surplus

Backfill = excavation − concrete below ground level − blinding layer. The surplus is excavation minus backfill – that is, exactly what concrete and blinding layer take up in the ground. Without reuse, the whole excavation is surplus. For transport, the loose volume counts: loose = in place · bulking.

Four foundations per tower

A lattice tower on four legs has four single foundations. The quantities of one foundation are then multiplied by the number 4 – if you forget it, you order a quarter. If the pits lie close together, a comparison with a common excavation pit is worthwhile: the excavation pit simulation has the shape with four beams for this.

Example – recalculated by the program

Slab 3.00 × 3.00 × 0.80 m with plinth 1.00 × 1.00 × 1.60 m, founded 2.00 m deep, 60° slope

Step 1 (slab): 3.00 × 3.00 × 0.80 mStep 2 (plinth): 1.00 × 1.00 × 1.60 mFounding depth: 2.00 mBlinding layer: 0.05 mWorking space / slope: 0.50 m / 60°

QuantityCalculationResult
Concrete3.00 · 3.00 · 0.80 + 1.00 · 1.00 · 1.608.80 m³ · 21.1 t
Formworkside faces of both steps16.0 m²
Blinding layerslab footprint with projection · thickness0.51 m³
Excavation pitfounding depth + blinding layer; bottom + 2 · depth ÷ tan 60°2.05 m deep, 6.37 m wide at the top
Excavation, in situfrustum: t ÷ 6 · (a·b + (a + a′)·(b + b′) + a′·b′)56.04 m³
Backfillexcavation − concrete below ground − blinding layer47.13 m³
Surplus soilexcavation − backfill8.9 m³

With an excavation pit at the same location the foundation takes over its dimensions – and the comparison shows every deviation.

The figures are calculated by the same calculation core as in the application – every time this page is called up.

Limits

  • The tool determines quantities and designs nothing: dimensions, concrete grade, reinforcement and foundation depth are specified by the structural design and the ground investigation report.
  • The calculation does not replace a stability analysis of the foundation or the tower.
  • The excavation is calculated by formula for level terrain; the excavation pit simulation calculates with a terrain model, connectors and berms and therefore arrives at different values.
  • Enter excavation pits deeper than 1.25 m only when sloped or shored.

This article is a working aid. It is not legal advice and does not replace specialist planning, a ground investigation report, structural analysis or a check by a competent person. The current editions of the standards and rules named here and the requirements of the client, the network operator and the authorities are authoritative. This is a translation; the rules cited are German and European ones, and the German version of this article prevails.

Sources and standards

  • DIN 4124 (excavations and trenches) for slope angle and working space of the pit.
  • Manual, chapter Foundation: calculation method and example.

Calculate a foundation Calculation method in the manual