Slope angle and working space according to DIN 4124

How steeply an excavation pit may be sloped depends on the soil – not on the space available. DIN 4124 names angles that apply without a calculated verification, and the conditions under which they apply.

As of: · baustellen.tools

Standard angles without verification

For slopes without a stability analysis, the excavation pit simulation calculates with these angles to the horizontal:

  • 45° in non-cohesive or soft cohesive soil
  • 60° in cohesive soil that is at least stiff
  • 80° in rock
  • down to a depth of 1.25 m, walls may stand vertical without support

When the standard angles are not enough

The angles apply to simple conditions. A stability analysis (DIN 4084) is needed, among other cases, if the slope is higher than 5 m, if the slope is to be steeper than the soil allows, or if loads, water or neighbouring buildings come into play. At the top edge of the slope, a load-free protective strip of at least 0.60 m remains.

Working space and berms

Between the structure and the toe of the slope you need room to work: at least 0.50 m in a sloped excavation pit, 0.60 m in front of shoring. The working space is added all round to the dimensions of the structure – if you enter the dimensions of the pit base instead of the structure, you count it twice.

High slopes are interrupted by berms, horizontal steps at least 0.60 m wide, usually 1.50 m. For this, the simulation divides the slope height into sections of equal height: a height of 4.50 m with a step height of 3 m gives two sections of 2.25 m and one berm.

What the angle means for the quantity

The excavation of a sloped pit grows with the square of the depth: on top of the prism above the base come the slope wedges along the sides and rounded corners. For a rectangle in level terrain with base area A, base perimeter U, depth T and slope angle β: V = A · T + U · T² ÷ (2 · tan β) + π · T³ ÷ (3 · tan² β).

Example – recalculated by the program

Excavation pit 10 × 8 m, 3.00 m deep, working space 1.00 m – once at 45°, once at 60°

Structure: 10 × 8 mFoundation depth: 3.00 mWorking space: 1.00 mGround: level

QuantityCalculationResult
Excavation at 45°non-cohesive or soft cohesive soil586.3 m³
Excavation at 60°cohesive soil, at least stiff483.7 m³
Difference586.3 − 483.7102.5 m³ (17 % less)
Excavated areaarea that is excavated280 m² at 45°, 206 m² at 60°

Which angle applies is determined by the soil – not by the space on the plot. The steeper angle is only permissible if the soil allows it.

The figures are calculated by the same calculation core as in the application – every time this page is called up.

Limits

  • The simulation calculates slopes; it does not verify their stability.
  • Soil, groundwater and the permissible angle come from the ground investigation report.
  • Shoring is calculated as a vertical wall without thickness; its design and its embedment below the base are not included.
  • The tool does not assess dewatering, traffic loads or neighbouring buildings.

This article is a working aid. It is not legal advice and does not replace specialist planning, a ground investigation report, structural analysis or a check by a competent person. The current editions of the standards and rules named here and the requirements of the client, the network operator and the authorities are authoritative. This is a translation; the rules cited are German and European ones, and the German version of this article prevails.

Sources and standards

  • DIN 4124 (excavations and trenches – slopes, shoring, working space widths).
  • DIN 4084 (stability analysis), to which the checklist refers; DGUV Regel 101-038 (construction work).
  • Manual, chapter Excavation pit simulation: assumptions, calculation method and the example calculation by hand.

Calculate an excavation pit with slope and working space Calculation method in the manual