Site layout plan: what belongs in it and how to build it up

A site layout plan answers three questions: What stands where? When does it stand there? And does it all fit together? If you keep it to scale and with dates, you see bottlenecks before the first container arrives.

As of: · baustellen.tools

What the plan shows

The plan is a true-to-position top view of the site – ideally on top of an aerial image or site plan, so that boundaries, trees and neighbours are in the picture. It contains:

  • access, gates and site roads – with the width the largest vehicle needs
  • crane and equipment positions with slewing range and working space
  • storage, assembly and loading areas, stockpiles
  • containers for office, break room, sanitary facilities and stores
  • the excavation pit with its top edge, exclusion areas and site fence
  • waste disposal, power and water connection, assembly point

In which order it is drawn up

It has proved useful to go from what cannot be moved to what can: first the position (coordinate, aerial image), then fence and access, then the excavation pit, then crane and equipment, and storage and containers last. What is fixed early restricts everything that follows – the crane has to reach the structure, the deliveries have to reach the crane.

Why construction phases belong to it

A site looks different during the shell construction than during excavation. Instead of drawing a separate plan for each phase, every object gets its own period. Then you can say for every day what is standing – and whether two things overlap: two objects collide if their areas overlap and their periods have at least one day in common.

The same data gives the area demand over the construction period: at every sampling point – every seven days, for example – you add up the areas of all objects that are active on that day. The peak shows when space gets tight.

Quantities come as a by-product

If you draw areas to scale, you already have the quantities of the surfacing: crushed stone is area times layer thickness, in tonnes with a conversion value (1.8 t per m³ as the default in the tool). A site road 120 m long and 4 m wide with 30 cm of crushed stone needs 480 m² · 0.30 m = 144 m³, that is 259.2 t.

Example – recalculated by the program

Example project “Stadtquartier Lindenhof”, plot A: what the plan says about the construction period

Objects in the plan: 50Construction phases: 8Construction period: 01.03.2027 – 02.03.2029

QuantityCalculationResult
Construction periodfirst to last day, both included733 days
Sampling pointsevery 7 days and the last day106
Peak area demandsum of all areas that are active on that day2,502 m² on 08.01.2029
Area types in the balanceone curve per type9

The example project is in every account: Projects › Example projects. All data in it are invented.

The figures are calculated by the same calculation core as in the application – every time this page is called up.

Limits

  • The plan is a flat top view: it does not show whether a jib slews over a building, an overhead line or a second crane.
  • Lifting capacities from the equipment database are an approximation – for the operation, the manufacturer's load charts and the crane operator's lift planning are what count.
  • The bearing capacity of set-up and driving surfaces, outrigger pressures and distances to slopes have to be verified separately.
  • The plan is not an official site plan and not a traffic sign plan ordered under road traffic law.

This article is a working aid. It is not legal advice and does not replace specialist planning, a ground investigation report, structural analysis or a check by a competent person. The current editions of the standards and rules named here and the requirements of the client, the network operator and the authorities are authoritative. This is a translation; the rules cited are German and European ones, and the German version of this article prevails.

Sources and standards

  • Baustellenverordnung (BaustellV, German construction site ordinance) and the German workplace rules (ASR) – for setting up the site; the plan depicts them but does not check them.
  • Manual, chapter Site layout: assumptions, calculation method for areas, overlaps, area demand and quantities.

Draw a site layout plan in the browser Calculation method in the manual