Skip to content

Pipe trench: minimum width according to DIN EN 1610

The width of a pipe trench does not follow from the pipe alone. DIN EN 1610 names two minimum values – one from the nominal size, one from the depth. The larger one applies.

As of: · baustellen.tools

Minimum width from the nominal size

An allowance that grows with the nominal size is added to the outside diameter OD. For shored trenches and for slopes steeper than 60°:

  • up to DN 225: OD + 0.40 m
  • over DN 225 up to DN 350: OD + 0.50 m
  • over DN 350 up to DN 700: OD + 0.70 m
  • over DN 700 up to DN 1200: OD + 0.85 m
  • over DN 1200: OD + 1.00 m
  • sloped up to 60°: OD + 0.40 m for every nominal size

Minimum width from the depth

Regardless of the pipe, the depth requires room to work:

  • less than 1.00 m: no requirement
  • 1.00 m to 1.75 m: 0.80 m
  • over 1.75 m up to 4.00 m: 0.90 m
  • over 4.00 m: 1.00 m

From the cross-section to the quantities

With base width b, depth T and slope angle β, the cross-section is A = b · T when shored and A = b · T + T² ÷ tan β when sloped. The excavation is A times length.

The pipe zone reaches from the base to above the cover: height = lower bedding layer + OD + cover. Its material is the cross-section up to this height times length, less the pipe. Above it lies the main backfill. What remains as surplus soil is the excavation less the main backfill and the surface layers.

Typical mistakes

  • Depth entered to the pipe invert instead of the trench base – the bedding is then missing.
  • Outside diameter forgotten: a concrete pipe DN 500 has an outside diameter of about 0.65 m.
  • Slope as a ratio instead of an angle: 1 : 1 is 45°, 1 : 0.58 is 60°.

Example – recalculated by the program

50 m trench, 2.00 m deep, DN 300, vertical with shoring

Trench length: 50.0 mTrench depth: 2.00 mNominal size: DN 300Trench wall: vertical with shoringBedding / cover: 0.10 m / 0.30 mBulking factor: 1.25

QuantityCalculationResult
Bottom widththe larger of OD + 0.50 m = 0.80 m and the minimum width for the depth = 0.90 m0.90 m
Excavation, in situ0.90 · 2.00 · 50.090.0 m³
Excavation, loose90.0 · 1.25112.5 m³
Pipe zone materialbedding, sidefill and cover, without the pipe28.0 m³ · 50.3 t
Main backfillfrom the pipe zone to the surface58.5 m³
Surplus soil, in situexcavation − main backfill31.5 m³
Shoring area2 · depth · length200 m²

These are the example values the tool starts with.

The figures are calculated by the same calculation core as in the application – every time this page is called up.

Limits

  • Preliminary sizing: no structural analysis of the pipeline, no design of the shoring, no stability analysis.
  • Straight trench with constant cross-section in level terrain; manholes, joint pits and crossings are not included.
  • The minimum widths are those of DIN EN 1610 for drains and sewers; for pressure pipes, gas, district heating and cables, the rules of the network operator apply in addition.
  • Enter trenches deeper than 1.25 m only when shored or sloped.

This article is a working aid. It is not legal advice and does not replace specialist planning, a ground investigation report, structural analysis or a check by a competent person. The current editions of the standards and rules named here and the requirements of the client, the network operator and the authorities are authoritative. This is a translation; the rules cited are German and European ones, and the German version of this article prevails.

Sources and standards

  • DIN EN 1610 (construction and testing of drains and sewers): minimum trench width, bedding, cover.
  • DIN 4124 (excavations and trenches): slope angles, vertical walls, shoring.
  • The values in the tool are checked against documents that reproduce the standards (BG BAU, DWA-A 139, standard sheets of network operators), not against the text of the standards themselves.
  • Manual, chapter Trench: calculation method, both tables and example.

Calculate a pipe trench Calculation method in the manual