Contents
- Basics
- 1Getting started
- 2Projects
- 3Locations
- Plans
- 4Site layout
- 5Escape and rescue plan
- Civil works
- 6Excavation pit simulation
- 7Foundation
- 8Trench
- Tower construction
- 9Tower assembly check
- 10Span (conductor)
- Cable construction
- 11Cable route and cable pulling
- 12Cable drum
- Team, subscription and account
- 13Working together
- 14Subscription
- 15Account
- Help
- 16Phone and tablet
- 17Keyboard shortcuts at a glance
- 18Frequently asked questions and messages
- 19What’s new
8 Trench
A pipe trench from a few inputs: minimum width to EN 1610, excavation, pipe zone material, backfill and surplus soil – with a checklist.
Creating, calculating, saving
- Create: on the location page, the card Trench › Create trench and calculate. There is one trench per location; the card then shows nominal size, length, depth, excavation, base width, pipe zone and surplus, and Open leads back to it.
- Calculate: at the left the inputs in three groups – Trench, Pipe and pipe zone, Backfill and disposal –, at the right the result. Every change is calculated immediately. For an input that is not permitted, the page names the field and the range; the last valid result remains, shown faintly.
- Save or CtrlS stores inputs and result at the location; the time is shown next to it. If someone else has saved in the meantime, the page reports this and overwrites nothing.
- Delete: on the location page in the menu ⋯ of the card. With the location, its trench is deleted, moved or archived as well.
- Whoever has read-only access in the project can view and calculate but not save.
Inputs
- Trench length, trench depth
- in m. The depth runs from ground level to the trench base – that is, to below the lower bedding layer.
- Trench wall
- vertical with shoring or sloped with the slope angle in degrees from the horizontal. The soil according to DIN 4124 determines how steep the slope may be without analysis: 45°, 60° or 80°.
- Base width
- leave empty – then the minimum width to EN 1610 applies – or enter your own value in m, for example the width of the trench box. If it is smaller than the minimum width, the checklist says so.
- Nominal size DN, outside diameter
- DN in mm determines the minimum width. The outside diameter OD in m determines width, pipe zone and pipe displacement; empty means the same as DN. For pipes whose nominal size is the inside diameter (concrete, vitrified clay), enter the manufacturer’s outside diameter.
- Lower bedding layer, cover
- in m: the layer beneath the pipe (default 0.10 m) and the one above the pipe crown (default 0.30 m). Together with the pipe they make up the pipe zone.
- Placed density
- in t/m³ (default 1.8): converts the pipe zone material from m³ to tonnes.
- Topsoil or road construction
- thickness in m of the top layer that is not backfilled with excavated soil – topsoil that is stored separately, or the road construction.
- Reuse, bulking
- With the tick, the excavated soil is reused in the main backfill; without it, all the subsoil is removed. Bulking is a factor (default 1.25) for the volume when loosened.
Result
- Four tiles: excavation (in situ and loose), base width with minimum value, pipe zone material in m³ and t, surplus subsoil.
- Cross-section, to scale: pipe zone, main backfill, surface layer and pipe, with base width, depth and – when sloped – the width at the top.
- Checklist to EN 1610 and DIN 4124: trench width, slope angle or shoring, lower bedding layer, cover. Each item is met, observe, check or not permitted.
- Quantities: every quantity with value, unit and the calculation it comes from. Copy quantities (for Excel) Subscription puts the table on the clipboard.
- Download as PDF Subscription produces a sheet for the file: inputs, key figures, cross-section, checklist and quantities. The PDF comes from the server, laid out like all PDF outputs: header with location and project, footer with page number and the note “planning aid”. It contains what is currently in the form – saved or not.
- The project page shows the trench at its location, the project overview the number of trenches and their excavation.
Purpose, assumptions and limits
- Purpose
- Determine the quantities of a pipe trench quickly and transparently and check the standard values for width, slope, bedding and cover.
- Typical use
- Sewer, water, gas and cable duct trenches in tendering and work preparation; demand for bedding material and disposal; comparing shoring and slope; area of road surface to be broken up.
- For whom
- Civil engineering and pipeline construction, estimating, site management, work preparation.
- Units
- Lengths in m, nominal size in mm, angles in degrees, areas in m², volumes in m³ (in situ = undisturbed soil, loose = in situ × bulking), material in t. Both decimal comma and decimal point are accepted.
- Assumptions
-
- Straight trench with a constant cross-section in level terrain; one depth over the whole length.
- Sloped means: both sides at the same angle, without berms.
- Shored means: vertical walls; the base width is the clear width between the shoring walls. The thickness of the shoring is added on the outside and is not calculated.
- The pipe zone extends over the whole trench width, from the base to above the cover.
- Placed volume equals in-situ volume: the backfill is compacted to the density of the undisturbed soil.
- Technical limits
-
- No structural design of the pipeline, no design of the shoring, no stability analysis, no dewatering.
- Not included: manholes, joint holes at the pipe joints, widenings, gradient of the base, crossings with other services, several pipes in one trench, stepped trenches.
- Whether the excavated soil is suitable for reuse is decided by the soil investigation – the calculator takes it as you tick it.
- The minimum widths are those of EN 1610 for drains and sewers. For pressure pipes, gas, district heating and cables, the rules of the network operator apply in addition (in Germany for example DVGW W 400-2) – they may require more.
- Permitted inputs: length 0.1 to 100,000 m, depth 0.2 to 20 m, DN 20 to 4000, base width 0.2 to 20 m, slope angle 10 to 90°, bedding 0 to 1 m, cover 0 to 2 m, surface layer 0 to 3 m, bulking 1.0 to 3.0, placed density 0.5 to 3.5 t/m³.
- Regulations
- EN 1610 (construction and testing of drains and sewers; in Germany DIN EN 1610): minimum trench width, bedding, cover. DIN 4124 (excavations and trenches, German standard): slope angles, vertical walls, shoring. The values in the calculator have been checked against documents that reproduce the standards (BG BAU, DWA-A 139, network operators’ guidelines), not against the text of the standards themselves. What counts is the current edition; outside Germany, the local rules apply.
- Data protection
- What is stored are the inputs, a summary of the result and who saved when – at the location, visible to everyone who may open the project. The calculator does not ask for personal data. More in the privacy policy (German).
Calculation method, formulas and example
Minimum width to EN 1610 – the larger of the two values applies:
| Nominal size | shored, or sloped steeper than 60° | sloped up to 60° |
|---|---|---|
| up to DN 225 | OD + 0.40 m | OD + 0.40 m |
| above DN 225 to DN 350 | OD + 0.50 m | OD + 0.40 m |
| above DN 350 to DN 700 | OD + 0.70 m | OD + 0.40 m |
| above DN 700 to DN 1200 | OD + 0.85 m | OD + 0.40 m |
| above DN 1200 | OD + 1.00 m | OD + 0.40 m |
| Trench depth | Minimum width |
|---|---|
| below 1.00 m | no requirement |
| 1.00 m to 1.75 m | 0.80 m |
| above 1.75 m to 4.00 m | 0.90 m |
| above 4.00 m | 1.00 m |
Cross-section with base width b, depth T and slope angle β:
shored: A = b · T sloped: A = b · T + T² ÷ tan β width at the top = b + 2 · T ÷ tan β
excavation = A · L loose = in situ · bulking
Pipe zone with lower bedding layer a, outside diameter OD and cover c:
height = a + OD + c material = (cross-section up to this height) · L − π · OD² ÷ 4 · L
The main backfill is the cross-section between the pipe zone and the underside of the surface layer, times length. Surplus subsoil:
surplus = excavation − surface layer − main backfill (without reuse: excavation − surface layer)
Shoring area = 2 · T · L (both walls, without embedment). Surface broken up = width at the top · L.
| Quantity | Calculation | Result |
|---|---|---|
| Minimum width | from the nominal size 0.30 + 0.50 = 0.80 m; from the depth 0.90 m | 0.90 m |
| Excavation | 0.90 · 2.00 · 50 | 90.0 m³ in situ, 112.5 m³ loose |
| Pipe zone | height 0.10 + 0.30 + 0.30 = 0.70 m; 0.90 · 0.70 · 50 − π · 0.30² ÷ 4 · 50 = 31.5 − 3.5 | 28.0 m³, 50.3 t |
| Main backfill | 0.90 · (2.00 − 0.70) · 50 | 58.5 m³ |
| Surplus | 90.0 − 58.5 | 31.5 m³ in situ, 39.4 m³ loose |
| Shoring area | 2 · 2.00 · 50 | 200 m² |
The surplus here is exactly what pipe zone and pipe take up in the trench. With these inputs the calculator shows the same values.
Typical input errors:
- Depth entered to the pipe invert: the trench base is meant. Invert depth plus wall thickness plus lower bedding layer gives the trench depth.
- Outside diameter forgotten: a concrete pipe DN 500 has an outside diameter of roughly 0.65 m. If the field stays empty, the calculator uses 0.50 m – the trench becomes too narrow and the pipe zone too small.
- Outside diameter in millimetres: the field expects metres (0.65), the nominal size millimetres (500).
- Slope as a ratio: the angle from the horizontal is meant – 1 : 1 is 45°, 1 : 0.58 is 60°.
- Bulking as a percentage: enter 1.25, not 25.
- Surface layer thicker than the space above the pipe zone: the page names the field – reduce the thickness or deepen the trench.
Nothing found. Try another word – “fence” instead of “fencing”, say – or look in the <a class="hdb-siehe" href="/en/manual/faq">frequently asked questions.
Something missing or unclear? Write to info@baustellen.tools.